Step 1: List and prioritize the factors  affecting the timeline
Note issues such as equipment and material  availability, skilled personnel, and customer requirements that should  be considered for the following factors when developing a project  timeline. Consider the possibility that the project might not begin on  the proposed start date.
Equipment  order and delivery
Service  installation, such as WAN links
Customer schedule, including available  maintenance and downtime windows
Availability of appropriate technical  personnel
Step 2: Complete the time details for  each installation phase
The FilmCompany network upgrade is linked to  the StadiumCompany network redevelopment. It would be efficient to align  the FilmCompany stadium remote site work with that project. The  StadiumCompany RFP states that the project must be completed during the  off-season for the two teams. This requirement gives the project a  timeline of four months, which can be also applied to the FilmCompany  upgrade.
a. On the  table created in Lab 9.2.1 for Phase 1, fill in the Date information:
- Install Distribution and Core Layer equipment
- Configure new IP addressing & VLAN scheme
- Configure routing
b. On the table for Phase 2, fill in the Date  information:
- Upgrade the  WAN connectivity
- Extend the network to the remote site
- Configure Access Control Lists & security
c. On the table for Phase 3, fill in the Date  information:
- Install and  configure the wireless and associated mobility network equipment
Step 3:  Consider customer-caused delays
Customers may make changes to the  requirements during the installation of a project. When changes occur,  the timeline is used to make adjustments to personnel and other  available resources. The timeline
documentation can also be used to show the  customer how delays affect the project completion date.
Based on the timeline, write a project  variation statement showing the possible delay in the project completion  date if the FilmCompany decided at this stage to relocate an additional  three production staff and their workstations to the stadium.
Step 4: Using project management  software (Optional)
Project management tools such as Microsoft  Project can be used to create a project timeline. This software can be  useful for:
- Tracking the  progress of the project
- Keeping the project on schedule
- Identifying milestones
- Tracking labor assignments and costs
- Alerting the designer if the project is  falling behind schedule.
 
 