Step 1: List and prioritize the tasks that  require downtime on the current network
List the  tasks that require network downtime.
Step 2: Document the required downtime on the  project timeline
Sometimes it  is not possible to complete all of the required tasks during an  approved maintenance window. If an installation task requires the  network, or part of the network, to be down during normal business  hours, it is important to obtain permission from the customer. As soon  as the time frame is determined and approved, all the people involved  need to be notified accordingly.
a. List  those tasks that can be completed during a scheduled maintenance window.
b. List  those tasks that require the network to be down during normal business  hours.
Step 3: Document customer approved downtime
a. Indicate  on the Installation Plan Timeline when the network downtime will occur.
b. Include a  provision for customer approval to be recorded for this downtime.
c. Include a  task that requires that the users who will be affected are notified  with adequate advance notice of the network downtime. Ensure that the  users are also notified when the network or service returns to full  operation.
 
 